The annual plan to reduce the size of storage capacity (services)

Date/duration
Storage capacity reduction
Adverse impact on quality of services Note
Operating volume Injection output Extraction output
2nd – 4th May 2017 170 mil.m3 at 50% of max.rate at 0% of max.rate    Maintenance of gas pipeline Brumovice-Uhřice
1st  – 12th Nov 2017 190 mil.m3 0 m3/day 0 m3/day   Maintenance at MS Brumovice 
13th Sept 2018, 20th Sept 2018 250 mil.m3 at 83% of max.rate at 83% of max.rate Limitation caused by N4G (cleaning of pipeline DN 700 RU Mutěnice – PRS V.Němčice)
24th Sept 2018 – 1st Oct 2018 250 mil.m3 0 m3/day 0 m3/day Planned maintenance of UGS Dambořice
30th Oct 2018, 1st Nov 2018 250 mil.m3 at 50% of max.rate at 50% of max.rate Limitation caused by N4G (cleaning of pipeline DN 700 RU Mutěnice – PRS V.Němčice)
1-st June – 19-th Sep 2019 298 mil.m3 0 % 100 % planned Construction
20-th – 30-th Sep 2019 298 mil.m3 100 % 100 % planned Construction
1-st Oct – 15-th Dec 2019 298 mil.m3 0 % 100 % planned Construction

Updated on 10th December 2018